|
Project management Home > Tip library > Project management tipsIn some large projects, the project manager asks each team member to update the workplan with a current status and effort hours (if the effort hours are being tracked). In this scenario, the team members normally indicate whether their assigned work is completed. If not, they identify the percentage of the activity that is complete, or adjust the end date to reflect when the activity will be complete. They can also plug in their actual effort hours for each activity so far. In most cases, team members are not allowed to assign themselves to new work, add new activities or otherwise alter the workplan. After the team members update the plan with current status, the project manager can begin to evaluate the overall project status.
|
|||||
|
|
|||||
|
|
|||||
Copyright © 2004-2010 Visitask - Project management tips |
|||||